The Norwegian Airport at Gardermoen had to create a temporary bypass to keep the traffic from and to the Arrivals going, when reconstructing a concrete fly-over.

For the Norwegian Statens Vegvesen, we have installed a temporary bridge in one of the supply roads to the airport terminal in the Norwegian capital Oslo.

 

Janson Bridging has supplied 10 elements 21 meters long and 2.1 meters wide for this site, including a specially made triangular corner element. Janson Bridging took care of the design of the superstructure, the pre-assembly and the transport. Statens Vegvesen installed the bridge.

 

Teilen auf:

Einzelheiten zum Projekt

Lösungen
Trägerbrücke
Typ
JSK
Lösung
Traffic bridge
Gesamtlänge der Brücke
105 m
Straßenbreite
4,2 m
Gewicht
250 tn
Anzahl der Felder
5
Installationsdatum
December 2014
Datum der Demontage
September 2015
Länge der Brücke
5 x 21 m